SCG's $5bn Long Son Complex to Restart in Q2 2027 on US Ethane
SCG targets a Q2 2027 restart for its $5bn Long Son complex in Vietnam, backed by a $500mn ethane upgrade and a 15-year deal for 1mn t/yr of US ethane. Vietnam revenue hit $1.9bn in nine months.

SPECIFICATION
- 1
Long Son Petrochemical Complex, a $5bn+ investment, is slated to resume operations in Q2 2027
- 2
SCG is spending about $500mn to add US-imported ethane as feedstock, under a 15-year contract for ~1 million tonnes per year
- 3
LSP suspended production around May 2026 after Middle East feedstock disruption — its second shutdown since commercial startup in September 2024
- 4
SCG's Vietnam revenue reached about $1.9bn in the first nine months of 2026; group adjusted cash EBITDA rose 19% to $1.76bn
- 5
Duy Tan broke ground on a VND900bn (~$35mn) expansion of its Long An plastics factory in Tay Ninh Province
Thailand's SCG expects its $5-billion-plus Long Son Petrochemical Complex (LSP) in Vietnam to resume operations in the second quarter of 2027, ahead of the original schedule, once a roughly $500-million upgrade allows the cracker to run on imported ethane.
The group announced the timeline on Tuesday alongside its business results for the first nine months of 2026 and an update on its Vietnamese investment projects.
What does the ethane switch change?
SCG is accelerating the upgrade so the complex can use ethane gas as an additional feedstock, with completion targeted for Q2 2027. Ethane will come from the United States, under a 15-year long-term supply contract covering approximately 1 million metric tons per year.
For buyers and competitors, the practical effects are straightforward:
- Greater flexibility in feedstock selection at the cracker
- Lower production costs per tonne of olefins output
- Improved competitiveness in a petrochemical market SCG itself describes as difficult
The restart date matters because LSP has been idle since around May 2026, when Middle East feedstock supplies were disrupted by regional conflicts. That was the second suspension since the complex began commercial production in September 2024 — a plant of this size sitting cold for over a year removes a major supply point from the Southeast Asian olefins and polymers map.
In plain terms: a $5bn complex that couldn't survive Middle East supply risk is being re-engineered around American ethane.
How did Vietnam perform for SCG?
Revenue from SCG's Vietnamese operations reached VND48.996 trillion (about $1.9 billion) in the first nine months of 2026.
Group-wide, adjusted cash EBITDA hit VND45.341 trillion ($1.76 billion), up 19 percent year on year. Profit rose 13 percent and sales revenue climbed 3 percent against the same period last year — a decent result in a period marked by volatile energy prices and geopolitical uncertainty.
What else is SCG building in Vietnam?
Duy Tan Plastics Manufacturing JSC, a member of SCG Packaging, has broken ground on an expansion of the Duy Tan Long An Plastics Factory in Tay Ninh Province, with an estimated investment of VND900 billion (nearly $35 million).
SCG President and CEO Thammasak Sethaudom said Vietnam continued to be an important market in the group's long-term growth strategy.
"Despite facing fluctuations in energy prices and geopolitical uncertainties, SCG continued to invest in projects, human resources and partnerships in Vietnam," he said.
The footprint behind that statement: 28 subsidiaries in Vietnam and more than 15,000 employees, operating across petrochemicals, building materials, packaging and logistics.
For anyone supplying or buying around LSP, the Q2 2027 restart window — pulled forward from the original plan — is the date to build into forecasts.
via Google News — Petrochemicals (Source)